FANUC Alarm PNT1-699 — %sTurbine Startup Test Not Complete
FANUC PNT1-699 (“%sTurbine Startup Test Not Complete”): The Bell Speed Control Startup Test for the turbine is not complete. First check: Check the Start Mode field on the Bell Speed SETUP menu to check the status of the Startup Test.
Updated 2026-08-29 · LogrobotLM reference
Description
The Bell Speed Control Startup Test for the turbine is not complete. This test must be performed before running the turbine.
Remedy · Remède
Check the Start Mode field on the Bell Speed SETUP menu to check the status of the Startup Test. Then, run the test if necessary.
Frequently asked · Questions fréquentes
- What does FANUC alarm PNT1-699 mean?
- FANUC PNT1-699 (“%sTurbine Startup Test Not Complete”): The Bell Speed Control Startup Test for the turbine is not complete. This test must be performed before running the turbine.
- How do you troubleshoot FANUC alarm PNT1-699?
- Check the Start Mode field on the Bell Speed SETUP menu to check the status of the Startup Test. Then, run the test if necessary.
Related codes / Codes liés
Indicative field information — the robot manufacturer's manual and safety procedures always prevail. Never bypass a safety device; apply lockout/tagout (LOTO) before any physical intervention. · Informations indicatives issues du terrain — le manuel du constructeur et ses procédures de sécurité font foi. Ne shuntez jamais un organe de sécurité ; consignez (LOTO) avant toute intervention physique. How this reference is built →